DLR - Eastern Gateway Parking Structure
1585 S MANCHESTER AVE, ANAHEIM CA 92802
Permits (4)
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit Activity (22)
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
New plan revision for BLD2025-06431
3 weeks ago
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
Permit updated: BLD2025-06431 · Log in to see what changed
1 month ago
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
Permit updated: BLD2025-06431 · Log in to see what changed
1 month ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Plan revision updated: BLD2025-06432-REV01 · Log in to see what changed
1 month ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit updated: BLD2026-00531 · Log in to see what changed
2 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
New plan revision for BLD2025-06432
2 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Permit updated: BLD2025-06432 · Log in to see what changed
3 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Permit updated: BLD2025-06432 · Log in to see what changed
3 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Permit updated: BLD2025-06432 · Log in to see what changed
3 months ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit updated: BLD2026-00531 · Log in to see what changed
5 months ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit updated: BLD2026-00531 · Log in to see what changed
5 months ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit updated: BLD2026-00531 · Log in to see what changed
5 months ago
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
Permit updated: BLD2025-06431 · Log in to see what changed
5 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Permit updated: BLD2025-06432 · Log in to see what changed
5 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
Permit updated: BLD2025-06432 · Log in to see what changed
9 months ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
Permit updated: BLD2026-00531 · Log in to see what changed
9 months ago
DLR - S Manchester Building - Demolition: 70,732 sq ft office building with utilities to be capped and foundation to remain.
New permit filed: BLD2026-00531
9 months ago
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
Permit updated: BLD2025-06431 · Log in to see what changed
10 months ago
DLR - East Parking Structure - New Commercial Construction: 3,115,680 sq ft 7-level open parking structure core and shell. 13,945 sq ft for (18) canopies. (129) light poles at roof level. Install 316 EV chargers. With limited mechanical, electrical and plumbing.
New permit filed: BLD2025-06431
10 months ago
DLR - East Parking Structure - Plumbing: Install onsite sewer and water. (BLD2025-06431)
New permit filed: BLD2025-06432
10 months ago