DCA - Coco Attraction Construction
Jan 1, 2026
DCA - Site Development - Disneyland Dr. - Site Work: Replace perimeter fence with new 727 ln. ft. x 16 ft. high fence and 21 ln. ft. x 16 ft. high gate. With electrical.
DCA - Block 500 - Demolition: Remove 775 sq. ft. storage shed building, 75 sq. ft. storage unit, 600 sq. ft. canopy attached to BLDG# 931, substation #210 and cap utilities throughout.
DCA - Substation #210/BOH - Site Work: 562 sq. ft. new canopy at side of building. Install (13) light poles and (9) EV-Chargers. 100 ln. ft. x 8 ft. high CMU wall and 99 ln. ft. x 8 ft. high chain link fence. With electrical and plumbing.